Result

Tsutsujigaoka No. 2 stormwater trunk line construction

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Apr. 2016
Location of Construction Sendai city, Miyagi Prefecture
Ordering party Sendai City Construction Bureau Sewerage Division Pipeline Construction Division
Pipe diameter Φ800mm
Distance L=74.3m
Type of soil Hard clay, Silt
Gravel size

Work summary

Nominal diameter φ800mm
Distance of pipe jacking L=74.343m
Type of soil Hard clay, Silt
N value 50
Percentage of gravel - %
Maximum gravel size mm
Groundwater level GL-3.20m
Overburden 4.31~4.56m
Underground obstacles Remaining oval liner plate shaft exists
Construction period Apr. 2016~Jun. 2016 (Day and night work 8.0h) 4.0 months

There was an oval liner plate shaft left on the pipeline, but this method was adopted because it was impossible to remove it from the ground due to the intersection and sidewalk.
The remaining oval liner plate shaft was cut diagonally, and the bearing wall concrete and liner plate were cut.

Discharged metal pieces

Discharged metal pieces

TBM arrival status