Result

Toyama Line Construction [National Highway 359]

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Oct. 2015
Location of Construction Toyama city, Toyama Prefecture
Ordering party INPEX CORPORATION
Pipe diameter φ800㎜
Distance L=59.7m
Type of soil Gravel soil
Gravel size 450mm

Work summary

Nominal diameter φ800mm
Distance of pipe jacking 59.75m
Type of soil Gravel mixed with boulders
N value 50
Percentage of gravel 70%
Maximum gravel size 450mm
Groundwater level GL-2.03m
Overburden 4.89m
Underground obstacles Insurance method Expressway foundation (possible presence of steel sheet piles and H-beams)
Construction period Daytime work (8.0h) Aug. 2015~Oct 2015 (2.0 months)

There are two highway foundations on the pipeline & there may be steel sheet piles & H-beams. It was a crossing pipe jacking work on National Highway 359.
Since it was under the national highway, it was difficult to remove the obstacle from the ground, so the milling mall method was adopted.
According to the construction results, there were no steel sheet piles & H-beams, but there was a reaction of electromagnetic wave forward exploration before & during the passage of the foundation.

There is an obstacle reaction on the front

There is an obstacle reaction on the right side