Construction details | High-density slurry type pipe jacking method with compatible type for underground obstruction |
---|---|
Method | Milling mole method |
Completion date | Dec. 2015 |
Location of Construction | Saitama city, Saitama Prefecture |
Ordering party | Saitama Prefectural Waterworks Maintenance Office |
Pipe diameter | φ800㎜ |
Distance | L=116.9m |
Type of soil | Silt mixed with sand |
Gravel size |
Nominal diameter | φ800mm |
---|---|
Distance of pipe jacking | 116.876m |
Type of soil | Silt mixed with sand |
N value | 0 |
Percentage of gravel | - |
Maximum gravel size | - |
Groundwater level | GL-1.5m |
Overburden | 7.37~5.33m |
Underground obstacles | Steel sheet pile(type Ⅲ) 1 place, PC pile (Φ200mm) 1 place |
Construction period | (Day and night work 8.0h) Oct. 2015~Dec. 2015 (2 months) |
Initially, it was constructed by the High-density slurry type pipe jacking method, but after 30 m from driving shaft, an obstacle was encountered.
After that, a survey and trial trench were conducted, and it was found that there was a leftover shaft.
It was also found that there is a box culvert foundation PC pile at 70m from the driving shaft.
After discussions with the authority, it was decided to extract the PC piles and restart with the milling mall method.
It took time to cut, but TBM was able to reach safely.