Result

Water distribution main pipe(500 mm) new construction and water distribution main pipe(600 mm) replacement work at 2 Nishidai, Itabashi-ku to 1 Nishidai, Itabashi-ku

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Nov. 2016
Location of Construction Itabashi-ku, Tokyo
Ordering party Tokyo Metropolitan Waterworks Bureau
Pipe diameter Φ1000mm
Distance L=64.385m
Type of soil Sandy soil
Gravel size

Work summary

Nominal diameter Φ1000mm
Distance of pipe jacking L=64.385m
Type of soil Sandy soil
N value 1~30
Percentage of gravel -%
Maximum gravel size -㎜
Groundwater level GL-2.16
Overburden 9.65m
Underground obstacles What seems to be steel sheet pile type III 817mm, H-beam(400mmx400mm), H-beam(350mmx350mm)
Construction period Apr. 2016~Nov. 2016

Initially, 300 mm of H-beam was confirmed on the pipeline, so the milling moll method was adopted, but as a result, 817 mm of steel sheet pile, 400 mm of H-beam and 350 mm of H-beam were cut.

Underground obstacles

Underground obstacles