Result

Reconstruction near 1 Nagata-cho, 2 Kasumigaseki, Chiyoda-ku Phase 2 Construction

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Aug. 2015
Location of Construction Chiyoda-ku, Tokyo
Ordering party Tokyo Metropolitan Bureau of Sewerage
Pipe diameter φ1500㎜
Distance L=94.7m
Type of soil Cohesive soil
Gravel size

Work summary

Nominal diameter φ1500mm
Distance of pipe jacking L=94.7m
Type of soil Cohesive soil
N value 1~2
Percentage of gravel -
Maximum gravel size -
Groundwater level GL-7.76m
Overburden 10.09m
Underground obstacles Initial: 2 places of reinforced concrete, addition: 6 places of H-beam (H250~H350)
Construction period Night work (8.0h) Apr. 2015~Aug. 2015 (3.5 months)

There may be two reinforced concrete on the pipeline & the pipe jacking work was under a arterial road with heavy traffic.

As a result of the construction, TBM hit an unexpected obstacle after cutting two places of reinforced concrete. Unexpected H-beams (H250~H350) were continuously cut at 6 locations.

Discharged concrete pieces