Ibo River crossing pipe jacking work

Construction details Slurry type pipe jacking method
Method Slurry type Mud max method
Completion date Apr. 2012
Location of Construction Himeji city, Hyogo Prefecture
Ordering party Osaka Gas Co., Ltd.
Pipe diameter φ1200mm
Distance L=260.0m
Type of soil Gravel soil
Gravel size φ450mm

Work summary

Nominal diameter
Distance of pipe jacking
Type of soil
N value
Percentage of gravel
Maximum gravel size
Groundwater level
Overburden
Underground obstacles
Construction period

Overburden 15m & within 260m of pipe jacking length, about 200m is the construction of the Ibo River tributary (Hayashita River) river crossing. The gravel rate was as high as 50%, & it was a construction to excavate a layer mainly composed of boulders. The water permeability was high, & troubles caused by lost circulation to occur, making it a very difficult site for the slurry type pipe jacking method.