Result

Gas pipeline installation work across Ise Bay

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Jan. 2013
Location of Construction Yokkaichi city, Mie Prefecture
Ordering party Toho Gas Co., Ltd.
Pipe diameter φ1000㎜
Distance L=68.5m
Type of soil Rubble, sandy soil
Gravel size Φ1000mm(Rubble)

Work summary

Nominal diameter φ1000mm
Distance of pipe jacking L=68.47m
Type of soil Rubble, sandy soil
N value 50
Percentage of gravel 80%
Maximum gravel size 1000mm(Rubble)
Groundwater level GL-2.80m
Overburden Average 6.9m
Underground obstacles Former revetment masonry (boulder) wire basket, tetrapod (launching to 30m section)
Construction period Daytime work (8h) Dec. 2012~Jan. 2013 (2 months)

Immediately after the launching, a masonry (boulder), wire basket, & tetrapod section of about 20m were excavated, & the remaining 38m was constructed by normal pipe jacking.
At this site, in addition to the excavation of the old revetment masonry (boulder), there was some kind of metal reaction as a result of prior magnetic exploration, so the milling mall method was adopted.
Obstacle masonry groups and tetrapods are very large for TBM with a nominal diameter of φ1000 mm, so it took time to cut.
The jacking pipe also uses a composite steel pipe with a rolling prevention function dedicated to milling moll method.
During the construction, crushed pieces of boulder & wire were excavated, and it was thought that the metal reaction was in this wire basket.

Former revetment masonry (boulder) excavated during the excavation of the driving shaft

Wire piece ejected during pipe jacking work