Construction details | High-density slurry type pipe jacking method with compatible type for underground obstruction |
---|---|
Method | Milling mole method |
Completion date | Oct. 2015 |
Location of Construction | Chuo-ku, Tokyo |
Ordering party | Tokyo Metropolitan Waterworks Bureau |
Pipe diameter | φ900㎜ |
Distance | L=196.0m |
Type of soil | Sandy soil, Cohesive soil |
Gravel size |
Nominal diameter | φ900mm |
---|---|
Distance of pipe jacking | 196.08m |
Type of soil | Sandy soil, Cohesive soil |
N value | 2 |
Percentage of gravel | - |
Maximum gravel size | - |
Groundwater level | GL-2.33m |
Overburden | 6.47m |
Underground obstacles | Insurance method (NTT's leftover sheet pile may exist) |
Construction period | Daytime work (8.0h) Oct. 2015~Dec 2015 (2.0 months) |
Initially, there was a possibility that the remaining sheet piles & wooden piles of the NTT shaft would come out at 50 m from the driving shaft, so the milling mall method was adopted, but TBM arrived without encountering any obstacles.