Construction details | High-density slurry type pipe jacking method with compatible type for underground obstruction |
---|---|
Method | Milling mole method |
Completion date | Nov. 2013 |
Location of Construction | Sasebo city, Nagasaki Prefecture |
Ordering party | Sasebo city |
Pipe diameter | φ800㎜ |
Distance | L=62.0m |
Type of soil | Sandy silt mixed with gravel |
Gravel size | φ52㎜ |
Nominal diameter | Φ800mm (Φ900 steel pipe microtunneling method) |
---|---|
Distance of pipe jacking | L=62.0m |
Type of soil | Sandy silt mixed with gravel |
N value | 2 |
Percentage of gravel | - |
Maximum gravel size | 52mm |
Groundwater level | GL-1.43m |
Overburden | 7.17m |
Underground obstacles | Steel sheet pile (typeⅢ) 2 places |
Construction period | Day and night work (16h) Nov. 2013~Nov 2013 (0.5 months) |
About 40 m after launching, the first obstacle (Steel sheet pile type III) was cut, & about 7 m was proceeded with normal pipe jacking.
After that, the second obstacle (Steel sheet pile type III) was cut & the remaining 15m was reached by normal pipe jacking.
This work was a water pipe laying work, in which a ductile pipe φ800 mm was inserted after penetrating a φ900 steel pipe.
Obstacles (Steel sheet pile type III) were used for revetment work during the construction of the Hizukushi bridge, & existed on both sides of the river.