Result

Among the planed supply works for the 1 Nishi-Shinbashi, the new construction of the Hibiya route cable tunnel (Phase 1)

Construction details 地中障害物対応型泥濃式推進工法High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Feb. 2012
Location of Construction Minato-ku, Tokyo
Ordering party Marunouchi Heat Supply Co., Ltd.
Pipe diameter φ2000㎜
Distance L=78.3m
Type of soil Sandy silt
Gravel size

Work summary

Nominal diameter φ2000mm
Distance of pipe jacking L=78.3m (Curve with R200m x 1 place)
Type of soil Sandy silt
N value 2
Percentage of gravel -
Maximum gravel size -
Groundwater level GL-4.05m
Overburden 18.35m~17.89m
Underground obstacles H-beam (300mm) x 4 places, 2 pieces per cross section x 4 places
Construction period Day and night work (16h) Dec. 2011~Feb. 2012 (2 months)

About 10 m after the launching, the first obstacle (H-beam, 300mm) was cut, and then the second and third H-beam (300mm) were cut at intervals of about 2 m. After that, we planned to cut the remaining 3 places of H-beams (300mm) until reception shaft.
However, TBM did not encounter the remaining three obstacles (H-beam, 300mm).

The first piece of metal discharged. It was cut in a fairly large state.

Discharged metal pieces. It was cut to about 1 cm.