2012 Onchi River East Drainage Zone (14th Construction Zone) Sewerage work

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Mar. 2015
Location of Construction Yao city, Osaka
Ordering party Yao city
Pipe diameter φ1000㎜
Distance L=229.2m
Type of soil Sandy soil and cohesive soil
Gravel size φ57㎜

Work summary

Nominal diameter φ1000mm
Distance of pipe jacking L=229.25m (Curve with R45m, R70m, R100m x 2, R200m)
Type of soil Sandy soil and cohesive soil
N value 4~35
Percentage of gravel -
Maximum gravel size 57mm
Groundwater level GL-3.39m
Overburden 6.44m
Underground obstacles H-beam 300mm x 2 places (One of two is unexpected)
Construction period Daytime work (6.0h) Jan. 2015~Mar. 2015 (3 months)

It was expected that H-beams (300mm) would be present on the pipeline near 5.5 m from the driving shaft. After cutting the first H-beam diagonally, TBM hit the second H-beam near 4m & cut diagonally as well. As a result, two H-beam (300mm) were cut. We also confirmed the discharge of metal pieces.

Discharged metal pieces

Discharged metal pieces