Result

2013 Onchi River East drainage zone (5th construction zone) Sewerage work

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Mar. 2015
Location of Construction Yao city, Osaka
Ordering party Yao city
Pipe diameter φ1650㎜
Distance L=325.4m
Type of soil Sandy soil and cohesive soil
Gravel size φ19㎜

Work summary

Nominal diameter φ1650mm
Distance of pipe jacking L=325.47m (Curve with R200m)
Type of soil Sandy soil and cohesive soil
N value 9~50
Percentage of gravel -
Maximum gravel size 19mm
Groundwater level GL-1.35m
Overburden 10.58m
Underground obstacles PC pile Φ250mm x 3 places
Construction period Night work (8.0h) Nov. 2014~Mar. 2015 (5 months)

It was expected that there would be support piles for the frontage road retaining wall (PC piles φ250 mm 3 places) on the pipeline. Traffic regulation was difficult because the road in the construction section was a arterial road with heavy traffic. Therefore, the milling molding method was adopted & three PC piles (φ250 mm) were cut.

Discharged metal pieces