Construction of water distribution mains around Hizukushimachi (Phase 6)

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date Nov. 2013
Location of Construction Sasebo city, Nagasaki Prefecture
Ordering party Sasebo city
Pipe diameter φ800㎜
Distance L=62.0m
Type of soil Sandy silt mixed with gravel
Gravel size φ52㎜

Work summary

Nominal diameter Φ800mm (Φ900 steel pipe microtunneling method)
Distance of pipe jacking L=62.0m
Type of soil Sandy silt mixed with gravel
N value 2
Percentage of gravel -
Maximum gravel size 52mm
Groundwater level GL-1.43m
Overburden 7.17m
Underground obstacles Steel sheet pile (typeⅢ) 2 places
Construction period Day and night work (16h) Nov. 2013~Nov 2013 (0.5 months)

About 40 m after launching, the first obstacle (Steel sheet pile type III) was cut, & about 7 m was proceeded with normal pipe jacking.
After that, the second obstacle (Steel sheet pile type III) was cut & the remaining 15m was reached by normal pipe jacking.
This work was a water pipe laying work, in which a ductile pipe φ800 mm was inserted after penetrating a φ900 steel pipe.
Obstacles (Steel sheet pile type III) were used for revetment work during the construction of the Hizukushi bridge, & existed on both sides of the river.

2013.11.7 Status of discharged steel sheet pile cutting powder

2013.11.7 Status of discharged steel sheet pile cutting powder