| Construction details | High-density slurry type pipe jacking method with compatible type for underground obstruction | 
|---|---|
| Method | Milling mole method | 
| Completion date | Aug. 2015 | 
| Location of Construction | Chiyoda-ku, Tokyo | 
| Ordering party | Tokyo Metropolitan Bureau of Sewerage | 
| Pipe diameter | φ1500㎜ | 
| Distance | L=94.7m | 
| Type of soil | Cohesive soil | 
| Gravel size | 
| Nominal diameter | φ1500mm | 
|---|---|
| Distance of pipe jacking | L=94.7m | 
| Type of soil | Cohesive soil | 
| N value | 1~2 | 
| Percentage of gravel | - | 
| Maximum gravel size | - | 
| Groundwater level | GL-7.76m | 
| Overburden | 10.09m | 
| Underground obstacles | Initial: 2 places of reinforced concrete, addition: 6 places of H-beam (H250~H350) | 
| Construction period | Night work (8.0h) Apr. 2015~Aug. 2015 (3.5 months) | 
            There may be two reinforced concrete on the pipeline & the pipe jacking work was under a arterial road with heavy traffic.
As a result of the construction, TBM hit an unexpected obstacle after cutting two places of reinforced concrete. Unexpected H-beams (H250~H350) were continuously cut at 6 locations.          