Result

Water distribution main laying work from 3 Nihonbashi Muromachi, Chuo-ku to 3 Nihonbashi-honcho, Chuo-ku

Construction details High-density slurry type pipe jacking method with compatible type for underground obstruction
Method Milling mole method
Completion date May. 2016
Location of Construction Chuo-ku, Tokyo
Ordering party P.S. Mitsubishi Construction
Pipe diameter φ1100㎜
Distance L=238.1m
Type of soil Clay, Silt
Gravel size

Work summary

Nominal diameter φ1100mm
Distance of pipe jacking 182.481m,55.656m
Type of soil Clay, Silt
N value 7~30
Percentage of gravel -
Maximum gravel size -
Groundwater level GL-4.93m
Overburden 15.12m
Underground obstacles Insurance method (PC pile, steel sheet pile may exist)
Construction period May. 2016~Aug. 2016 (Night work 8.0h) 3.0 months

There were two spans at this site, and there was a possibility that obstacles existed in both spans.
In the first span, there was a possibility that there was a steel sheet pile under the underground structure of TEPCO, and in the second span, there was a PC pile in the basement of Tokyo Metro Mitsukoshimae Station. However, it did not hit any obstacles and was able to reach it safely.
During the construction, there were many places where the magnetometer reacted, and in the section where it reacted, the jack speed was reduced.

Full view of the TBM cutter

TBM arrival status